where did you get that idea?

napkin sketches

  Public Art Installations

Public Art Installations (Coming Oct and Nov 2020)

DURATION

1) 4 months

2) 2 months

SIZE OF TEAM

1) 15 

2) 1

BUDGET

1) $15,000

2) $15,000

-Design and build 6ft fiberglass shoe for the Boston Sports Museum at TD Garden

-Fabricate and mount (7) 3ft tall words to a 140'x25' wall. 

 Table Dividers for Restaurants

DURATION

6 weeks 

Aug 2020

SIZE OF TEAM

2 of us

BUDGET

$5K each

8 Restaurants

30,000 Isolation Gowns for COVID

DURATION

40 weeks, April -now

SIZE OF TEAM

Gowns: 2-70

PPE at AA: 10

Nationawide leaders: 40

TOOLS

Ultrasonic Bonder/welder, fabric sutting machine, pnumatic squisher, impulse sealer

MATERIALS

landscape material, row cover, 2 mil plastic sheeting

Developed an assembly line and then taught hundreds of communities all over the country, on 5 continents to make hundreds of thousands of gowns. Eventually made prototypes for the US Govt. Received the largest grants. Partnered with national non-profit pandemic response leaders to create more productions line.

 

See 25 Page Document here for Patterns, Industry Standards, How- To, Tooling, Labeling, Spec Sheets, Safety Protocol, Sign Up sheets, Testing Results, Packaging, Timelines, Projections, Financial and Inventory Tracking, Etc.

Retail Signage

DURATION

a week per sign

anytime of year

SIZE OF TEAM

1

TOOLS

Plasma cutter, laser cutter, shopbot, welding

MATERIALS

PVP sheet, coreten, acrylic

Autonomous Electric Vehicle Prototype

DURATION

1 year

SIZE OF TEAM

1 Maker

1 Physisist

 1 Electrician

1 Owner

TOOLS

Handheald plasma cutter, welder, hydrolic impact gun, CNC plasma cutter, vacuum former

MATERIALS

2" tube steel, fiberglass, pleather, thermoform plastic, sintra, aluminum details

Body: I deconstructed the body of a 2004 Saturn and welded it to the existing 2" tube steel frame. 

Dashboard: CNC'd out of 2" slabs of 18lb foam.

Purchased: screens, seats, vents, speaker, buttons, steering wheel.

Machined: fold away cup holders, push-button start, face plates, door handles.

Integrated: swivel seats, reskinned door frames, gimbaled steering wheel.

Custom: windshield, fiberglassed exterior body.

 4 Residential Remodels

DURATION

19 months 

4 times over 7 years

SIZE OF TEAM

4-6

SKILLS

Cabinet install, framing, subfloors, built-ins, finish carpentry, windows, roofing, shingling, crown/basebaords

  BUDGET

Average $350,000

Restaurant Remodel

DURATION

4 months

SIZE OF TEAM

1 lead carpenter

1 maker

1 assistant

1 owner

TASKS

Build 25" bar

Epoxy 25' bar

-Install tin plate ceiling panels

-Build shelves from 300yr old mantels

-Refinish all architectural elements

  BUDGET

$1M

Corporate One-Offs- Winner of Both Contests

DURATION

1) 3 weeks

2) 3 weeks

SIZE OF TEAM

1-3

MATERIALS

pack, CNC shopbot, 3D printer

BUDGET

$5,000 for each

Other People's Art Installations 

DURATION

1 year to plan, 

2-3 weeks to build

SIZE OF TEAM

4-6

TOOLS

welder, shotbot, folklift, 

  BUDGET

Microchip $10,000

Typewriter $200,000

SIZE OF TEAM

1 Make

 Carpenter

1 Assistant

1 Owner

TOOLS

Table saw, circ saw

MATERIALS

Mahogony, douglas fur, pine, stain, stripper, nail gun, blowtourch